Contract Act, 1872 — Section 53: Liability of party preventing event on which the contract is to take effect
53. Liability of party preventing event on which the contract is to take effect. When a contract contains reciprocal promises, and one party to the contract prevents the other from performing his promise, the contract becomes voidable at the option of the party so prevented; and he is entitled to compensation from the other party for any loss which he may sustain in consequence of the non-performance of the contract. Illustration A and B contract that B shall execute certain work for A for a thousand rupees. B is ready and willing to execute the work accordingly, but A prevents him from doing so. The contract is voidable at the option of B ; and, if he elects to rescind it, he is entitled to recover from A compensation for any loss which he has incurred by its non-performance. 54. Effect of default as to that promise which should be first performed, in contract consisting of reciprocal promises. When a contract consists of reciprocal promises, such that one of them cannot be performed, or that its performance cannot be claimed till the other has been performed, and the promisor of the promise last mentioned fails to perform it, such promisor cannot claim the performance of the reciprocal promise, and must make compensation to the other party to the contract for any loss which such other party may sustain by the non-performance of the contract. Illustrations
(a)A hires B’s ship to take in and convey, from 1[Karachi] to the Mauritius, a cargo to be provided by A, B receiving a certain freight for its conveyance. A does not provide any cargo for the ship. A cannot claim the performance of B’s promise, and must make compensation to B for the loss which B sustains by the non-performance of the contract.
(b)A contracts with B to execute certain builder’s work for a fixed price. B supplying the scaffolding and timber necessary for the work. B refuses to furnish any scaffolding or timber, and he work cannot be executed. A need not execute the work, and B is bound to make compensation to A for any loss caused to him by the non-performance of the contract.
(c)A contracts with B to deliver to him, at a specified price, certain merchandise on board a ship which cannot arrive for a month, and B engages to pay for the merchandise within a week from the date of the contract. B does not pay within the week. A’s promise to deliver need not be performed, and B must make compensation.
(d)A promises B to sell him one hundred bales of merchandise, to be delivered next day, and B promises A to pay for them within a month. A does not deliver according to his promise. B’s promise to pay need not be performed, and A must make compensation.